Eatonville school district #404
eatonville high school modernization and addition pROJECT
school board REPORT February
28, 2007
|
SECTION
1 EXECUTIVE SUMMARY.
GENERAL
This report covers the status of the Eatonville High School
Modernizations and Addition project as of February 28, 2007.
Summary of critical milestones of project schedule is as
follows:
Date:
Meeting with Town Officials regarding Interim Housing 2/20/07
Meeting with Cabinet regarding Packing and Moving 2/22/07
Meeting with EHS and EMS Library regarding Interim Housing 2/26/07
Meeting with EHS and EMS Science regarding Interim Housing 2/26/07
Meeting with EHS Staff regarding Packing and Moving 2/27/07
Meeting with Portables Supplier regarding Interim Housing 2/27/07
Meeting with Boush Moving and
Storage 2/27/07
Public School Board Meeting Construction Report 2/28/07
DESIGN
Erickson McGovern is in the process of compiling the permit
review set of construction documents. The anticipated time for permit submittal
to the Town, State Fire Marshal, and other Agencies having jurisdiction is the
first week in March 2007.
Erickson McGovern and OAC are also working diligently with
sub-consultants to prepare permit review documents for the planned interim
housing of EHS at EMS.
SECTION
2 CRITICAL ISSUES
Critical issues are defined as issues that have had or may
likely have an impact on project cost, schedule or quality. The following is a list of issues considered
critical as of February
28, 2007:
- Temporary
Housing of EHS as it relates to Municipal Code
for the Town of Eatonville.
It is likely that the District will need to apply for the Conditional Use
Permit for both the Remodel / Addition and the
Interim Housing at EMS.
The District is in communications with the Town to identify requirements
and options. Concerns voiced by the Town Officials is that the District
assist with the cost of repaving Rainier Avenue, assist with the cost of 2
hour parking signage along the ancillary streets to encourage students to
use the proposed leased parking at the LeMays
property (old dealership), abandonment of the 6 parking stalls at the
front yard of EHS, and a No Left Turn Emergency Vehicles Only sign at
the island on Lynch Street leading to the parking lot that is located next
to North Hall. The District will continue discussions with the Town
regarding said concerns / requests.
- Electrical
Permit Review.
The Town does not currently have an Electrical Permit Reviewer on
staff or contracted for EHS. Erickson McGovern and OAC recommended to the
Town that they use L&I for this service as
does most local agencies.
- Budget Deficit.
Erickson McGovern has implemented the approved Value Analysis options and
has sent the revised construction documents to their estimator to update
the estimate. Erickson McGovern will have the updated estimate to the
District by the end of the week.
- Storage needs
for educational supplies, furniture, and equipment is being investigated
currently. Recommendations to the District will be made by the end of the
week regarding the most cost effective and secure method in which to store
those materials that will not be returning until the renovation and
additions are complete. The recommendation for temporary storage of the
materials that will be moving into the Interim Housing is that the
Gym/Aux. Gym be utilized over the summer. Further discussions with District
Administration will occur for both issues.
- Temporary pool
use for swim team is being investigated as the EHS pool will need to close
at the end of the 2006-2007 school year.
Discussions with Puyallup
School District
revealed that they cannot accommodate Eatonville
School District
with reasonable practice times due to commitments with other surrounding
school districts. The District is investigating pool use at Korum YMCA, PLU, Lacey
Community Center,
and North
Thurston
School District.
- Locker room
needs are being investigated as the EHS
locker rooms will not be available during the construction period. Further
information to follow in the next update.
SECTION
3 SCHEDULE
There has been an adjustment to schedule since the beginning
of design. With the implementation of
using the EMS
site to house EHS students and staff on an interim basis it is anticipated that
the project will be substantially complete in 20-22 months upon start of
construction.
SECTION
4 COST REPORT
This
section will be updated once the project is bid and contracted. The contract
amount and approved change orders will be in this section.
SECTION
5 CONSTRUCTION REPORT/CURRENT MONTH ACTIVITIES
This
section will be updated once construction begins
SECTION
6 LOOK AHEAD
Summary of the notable activities planned for the next
period.
- SEPA
/ Conditional Use Permit Submittal for EHS Modernization & Additions
and Interim Housing of EHS
- Order
portables for EHS / EMS
- Project
Manager attends EMS
staff meeting to discuss project and packing procedures for moving
- EHS
and EMS
Lunch and Safe Packing Procedures Demonstration
- Project
Manager, EMS/EHS Principals and Art
Department
meet regarding Interim Housing
- Project
Manager, EMS/EHS Principals and PE and Athletics meet regarding Interim
Housing
- Project
Manager, EMS/EHS Principals and Food Science meet regarding Interim
Housing
- Project
Manager and Superintendent meet with EHS Leadership to discuss Interim
Housing
SECTION
7 PHOTOS
This
section will be updated once construction starts and will show monthly
progress.