Multi-Year Technology Plan
1998
Phase I
Installation of K20 router.
Installation and configuration of central district router.
Installation and configuration of Columbia Crest router.
Installation and configuration of Weyerhaeuser Elementary router.
Installation and configuration of district wide e-mail enhancements and
synchronization's.
Installation and configuration of Internet and WWW systems and browser front
ends.
Install 7 administrative and other computers throughout the district
Phase II
Installation and configuration of network bridges in key areas of core network.
Install network concentrator/s at EMS computer lab.
Install 10 computers at CC computer lab.
Install web proxy and firewall.
1999
Phase I
Install memory upgrades at EMS computer lab.
Install network cards at EMS computer lab.
Install and configure web and Internet browsers and software at EMS lab.
Install memory upgrades at EES and WES labs.
Install 6 administrative and other computers throughout the district.
Phase II
Install network concentrators at EES and WES computer labs.
Install network cards at EES and WES labs.
Install and configure web and Internet software in EES and WES labs.
2000
Phase I
Install 6 administrative and other computers throughout the district.
Fiber optic cable connection upgrading 56kb link between the 2 main core
campuses.
Install network concentrator at CC computer lab.
Install 17 new computers at WES computer lab.
Install 17 upgraded computers at EES lab.
Phase II
Install 25 faculty use computers throughout the district.
Install 10/100 network switches in key wiring closets.
Install 100mbps network cards in key servers.
2001
Phase I
Install administrative and other computers throughout the district.
Training on video conferencing.
Install new student use computers at EMS.
Phase II
Install video conferencing equipment at EMS and EES.
Video conferencing utilized as key curriculum resource.
Install faculty use computers throughout the district.
Install 10/100 network switches in key wiring closets.
Install 100mbps network cards in key servers.
Upgrade office computers.
2002
Phase I
Upgrade office computers.
Install new student use computers at EHS.
Install wireless network access points (all buildings).
Install Internet Filtering systems.
Phase II
Upgrade office computers.
Install faculty use computers throughout the district.
Install 10/100 network switches in key wiring closets.
Install wireless network access points and cards in laptops and/or desktop pc's.
Install desktop IP video conferencing systems (all schools).
2003
Purchase and install computers for certified staff.
Purchase and install software district wide.
Upgrade office technology.
2004
Purchase and install computers for certified staff.
Purchase and install software district wide.
Upgrade office technology.
Review Schedule
This timeline to be reviewed a minimum of every 6 months. First planned review
scheduled for June, 1998.
Next scheduled review for this plan is: June, 2001.