Multi-Year Technology Plan
1998
Phase I
Installation of K20 router.
Installation and configuration of central district router including PIX (DHCP)box.
Installation and configuration of Columbia Crest router.
Installation and configuration of Weyerhaeuser Elementary router.
Installation and configuration of district wide e-mail enhancements and syncronizations.
Installation and configuration of Internet and WWW systems and browser front ends.
Install 7 administrative and other computers throughout the district
Phase II
Installation and configuration of network bridges in key areas of core network.
Install network concentrator/s at EMS computer lab.
Install 10 computers at CC computer lab.
Install Internet firewall/and filtering systems.
1999
Phase I
Install memory upgrades at EMS computer lab.
Install network cards at EMS computer lab.
Install and configure web and Internet browsers and software at EMS lab.
Install memory upgrades at EES and WES labs.
Install 6 administrative and other computers throughout the district.
Phase II
Install network concentrators at EES and WES computer labs.
Install network cards at EES and WES labs.
Install and configure web and Internet software in EES and WES labs.
Install 30 upgraded computers at EES lab.
2000
Phase I
Install 6 administrative and other computers throughout the district.
Fiber optic cable connection upgrading 56kb link between the 2 main core campuses.
Install network concentrator at CC computer lab.
Install 30 new computers at WES computer lab.
Phase II
Install 25 faculty use computers throughout the district.
Install 10/100 network switches in key wiring closets.
Install 100mbps network cards in key servers.
2001
Phase I
Install 6 administrative and other computers throughout the district.
Install video conferencing equipment.
Training on video conferencing.
Install 15 new student use computers at EMS.
Phase II
Video conferencing utilized as key curriculmn resource.
Install 25 faculty use computers throughout the district.
Install 10/100 network switches in key wiring closets.
Install 100mbps network cards in key servers.
2002
Phase I
Install 15 new student use computers at EHS.
Phase II
Install 25 faculty use computers throughout the district.
Install 10/100 network switches in key wiring closets.
Install 100mbps network cards in key servers.
Review Schedule
This timeline to be reviewed a minimum of every 6 months. First planned reviewal
schudled for June, 1998.